Friday 30th May, 7.30am-9am, Planned power outage in G Block at Canterbury Campus

Scheduled Maintenance Report for University for the Creative Arts

Completed

The scheduled maintenance has been completed.
Posted May 30, 2025 - 09:00 BST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted May 30, 2025 - 07:30 BST

Scheduled

Mitie will be carrying out some power maintenance work in G block on Friday 30th of May, from 07:30 AM until 9 AM. The work will require the replacement of some RCDs in the fuse boards, thus entails turning off the power in most of the building, which will affect the IT in that area as the switches, wireless access points and staff/student devices will be affected.
Posted May 29, 2025 - 14:32 BST
This scheduled maintenance affected: Infrastructure (Eduroam WiFi Services, Guest WiFi Services, Core Network, Campus Infrastructure Services, Telephony Services).